Leeds Central Station Upgrade
Major civil engineering works to increase platform capacity and improve passenger flow at a busy rail hub.
The Challenge
All construction had to be carried out while the station remained fully operational, demanding intricate phasing and night-time works to minimize disruption to the 100,000 daily passengers.
Our Solution
We developed a detailed 7-phase logistical plan in partnership with Network Rail. A temporary platform was constructed to maintain train services while the new platform was built. Most of the heavy structural work was completed during scheduled overnight possessions.
"This was one of the most complex operational environments we’ve managed. Stonebeam’s planning and execution were flawless."
- Richard Davis, Network Rail Programme Director